I. Project Background
As a traditional resource-based city undergoing urban renewal, Datong generates over 2 million tons of construction waste annually. The previous disposal method (open stacking + simple landfilling) resulted in low resource utilization (<25%), land occupation, and serious dust pollution. To fill the city's construction waste disposal gap and build an environmentally friendly society, this project was initiated to establish a large-scale, intelligent recycling base for both C&D waste and decoration waste.
II. Technical Parameters and Configuration
The system adopts a "bag tearing + screening + air separation + crushing + graded screening" process.
ParameterValue
Site Area76,000 m²
Total Investment~220 million RMB
Annual Capacity1.0 million tons (800 kt C&D waste + 200 kt decoration waste)
Annual OutputAggregates: 0-5mm (350 kt), 5-10mm (250 kt), 10-20mm (200 kt), 20-31.5mm (100 kt); Cement-stabilized macadam: 300 kt; Permeable bricks/blocks: 100 kt (~200,000 m²)
Key Equipment:
EquipmentSpecificationQty
Bag tearing machine80 t/h2
Heavy bar feeder≤800mm feed4
Jaw crusherPEV1100×750, 200 t/h2
Impact crusherPFW1315III, output ≤40mm2
Circular vibrating screen3 decks (5/10/20mm)4
Trommel screen60/30mm interchangeable2
Air separator100 t/h, efficiency ≥92%3
Magnetic separatorRCYD-124
Manual sorting platform4 stations2
Pulse bag filter80,000 m³/h, emission ≤10mg/m³3
Process Flow:
C&D waste: Feeding → coarse screening (soil removal) → jaw crushing → magnetic separation → impact crushing → air separation → graded screening → aggregates
Decoration waste: Bag tearing → trommel screening → air separation → manual sorting → crushing → screening → aggregates
Control System: DCS with centralized monitoring, auto load adjustment, fault diagnosis, interlock protection, and remote O&M interface.
Safety & Environmental Devices:
Enclosed building + negative pressure dust collection + spray system
Belt emergency pull cords + anti-deviation switches
Metal detector (prevents crusher damage)
Level monitoring + anti-blocking protection
Crusher sound enclosure + green belt noise reduction
III. Implementation Plan
3.1 Foundation and Mechanical Installation
Steel structure main workshop (approx. 20,000 m²) + office building (3,000 m²)
Concrete foundations with vibration isolators
Installation precision: crusher spindle horizontal error ≤0.15 mm/m; belt deviation ≤5 mm; trommel screen levelness ≤0.5 mm/m
3.2 Electrical and Control System Commissioning
Shielded cables + fiber optic ring network
DCS programming: crusher gap, screen size, air separator speed
Safety interlock test: response time ≤1 second
Interface with environmental monitoring platform for real-time emission data reporting
3.3 Trial Operation and Optimization
No-load test: 4 hours continuous; bearing temp rise ≤45°C; vibration ≤4.5 mm/s
Load test: Gradual loading 25% → 50% → 75% → 100%
Test C&D and decoration waste lines separately
Monitor: capacity, crusher current, screening efficiency (≥88%), air separation efficiency (≥92%)
Target product impurity rate ≤0.5%; final aggregates meet GB/T 25177 and GB/T 25176 standards
IV. Results
4.1 Resource Utilization
Utilization rate increased from <25% to >90%
Annual aggregate output: ~900 kt (four gradations)
Cement-stabilized macadam: 300 kt/year (for road base)
Permeable bricks/blocks: 100 kt/year (for sponge city construction)
Natural sand/gravel saved: ~850 kt/year
4.2 Environmental and Social Benefits
MetricResult
Fugitive dust≤0.5 mg/m³ (meets Shanxi standard)
Light material removal≥92%
Land saved~100 mu/year
CO₂ reduction~35,000 tons/year
Jobs created~60
Social valueFills Datong's disposal gap for next 10 years
Zero environmental penalties or major accidents since commissioning
Safety devices triggered successfully 20+ times (anti-blocking, overload, emergency stop, etc.)
4.3 Economic Benefits
MetricValue
Unit energy consumption≤5.8 kWh/ton
Annual revenue (disposal fees + product sales)~110 million RMB
Annual operating cost~65 million RMB
Annual net profit~38 million RMB
Payback period~5.8 years
Additional revenue includes government disposal subsidies.
Conclusion: This project demonstrates that a "bag tearing + screening + air separation + crushing + graded screening" system with DCS control and comprehensive environmental/safety features can achieve >90% resource utilization of mixed C&D and decoration waste. It provides a scalable model for resource-based cities undergoing transition.